Hackney Landlords — 1 May 2026 Compliance Checklist

On 1 May 2026 three regimes go live the same day — Hackney’s selective + additional HMO licensing schemes and the Renters’ Rights Act. Civil penalties up to £40,000 per offence, issued without warning. This is the page to print on the evening of 30 April 2026.

Stacked Changes Going Live 1 May 2026

  1. 1

    Hackney Selective Licensing (17 wards)

    Every privately rented property in 17 wards needs a £925 licence — not just HMOs. ~76% of Hackney's PRS in scope.

    Source: Cabinet 27 Nov 2025 · Gazette 5046077Hackney licensing page
  2. 2

    Hackney Additional HMO Licensing (borough-wide)

    All HMOs with 3–4 occupants forming 2+ households need a £1,400 licence. Section 257 HMOs excluded. Mandatory HMO scheme (5+ occupants) continues borough-wide at £1,400 from 1 April.

    Source: Cabinet 27 Nov 2025 · Gazette 5046077Hackney licensing page
  3. 3

    Renters' Rights Act commencement

    Section 21 evictions abolished, fixed-term ASTs converted to statutory periodic tenancies, deposit cap, £40,000 civil penalty regime, RRO 24-month window doubled.

    Source: Royal Assent 30 Oct 2025 · commencement 1 May 2026RRA guide
  4. 4

    £40,000 civil penalty regime live

    Maximum civil penalty quadruples from £30k → £40k for housing offences (licensing breaches included). Issued by Hackney without prior warning.

    Source: Renters' Rights Act 2025 §111RRA guide
  5. 5

    Section 8 Ground 8 hardening

    From 1 May 2026 Ground 8 rent-arrears notices may not be served unless the landlord can evidence current Gas Safety Certificate, EICR and EPC. No certs = no possession.

    Source: RRA 2025 transitional regsRRA guide
  6. 6

    Section 8 safety-cert gating (extended)

    All Section 8 grounds requiring 'reasonableness' now allow courts to refuse possession where landlord cannot produce valid safety certificates at hearing.

    Source: RRA 2025 §27 transitionalRRA guide
  7. 7

    RRO ceiling doubled (12 → 24 months)

    Tenants can apply for Rent Repayment Orders covering up to 24 months — backdated to before the RRA commences. Average award already £15k+ in London tribunals.

    Source: RRA 2025 §63 / RRO regsRRO calculator
  8. 8

    Written Information Sheet to tenants — 31 May deadline

    Landlords must serve a written 'information sheet' covering RRA tenancy rights to all current tenants by 31 May 2026. Failure is a civil penalty offence.

    Source: RRA 2025 commencement regsWritten Information page

Pre-1-May Checklist

  • Confirm whether your property sits in one of the 17 selective wards (see list below).
  • Apply on propertylicensing.hackney.gov.uk before 1 May 2026.
  • Renew Gas Safety Certificate (CP12) and email to gas.safetychecks@hackney.gov.uk.
  • Renew EICR if older than 5 years.
  • Confirm EPC current and at rating E+ (C+ unlocks Hackney's discount).
  • Install/test smoke alarms on every storey and CO alarms in every room with a fixed combustion appliance.
  • Fire Risk Assessment for HMOs.
  • If letting an HMO 3–4 occupants, file additional HMO application (£1,400).
  • Prepare and serve the written 'information sheet' to existing tenants before 31 May 2026.
  • Convert any fixed-term ASTs ending after 1 May to statutory periodic tenancy paperwork.
  • Audit deposit holdings against the new RRA cap.

The 17 Selective Licensing Wards

Get 3 Free Quotes — Hackney Compliance

Get the certificates Hackney needs for your licence application. Verified providers, no obligation.

Frequently Asked Questions

Why does 1 May 2026 matter for Hackney landlords?
Three things land on the same day: Hackney's selective and additional HMO licensing schemes go live, AND the Renters' Rights Act commences (Section 21 ban, statutory periodic tenancies, £40k civil penalty regime, doubled RRO window). It is the single largest compliance shift Hackney landlords have faced.
What's the worst-case fine if I'm not ready by 1 May 2026?
Up to £40,000 per offence under the new civil penalty regime — Hackney has confirmed these can be issued without warning. Plus unlimited fines on prosecution and Rent Repayment Orders of up to 24 months (RRA doubles the historic 12-month window).
Do I need a licence even if my Hackney property isn't an HMO?
If your property is in one of the 17 designated wards (see list above), YES — the selective scheme covers all PRS, including single-family lets. If it's a 3–4 occupant HMO, you also need an additional HMO licence (borough-wide). 5+ occupants need mandatory HMO licensing too.
What documents do I need to apply?
Gas Safety Certificate (CP12), EICR, EPC, evidence of smoke/CO alarms, fire risk assessment for HMOs. The RRA also forces these to be current to serve any Section 8 ground 8 (rent arrears) notice from 1 May 2026.
Where do I apply?
Hackney's licensing portal: propertylicensing.hackney.gov.uk. Email gas safety certificates to gas.safetychecks@hackney.gov.uk.
What about Section 8 grounds and the new Information Sheet?
The RRA tightens Ground 8 (rent arrears) — landlords must serve a separate written 'information sheet' to tenants by 31 May 2026 covering tenancy rights. Failure is itself a civil-penalty offence.