How Long Does an EICR Take in Barking and Dagenham?

Plan on roughly one week from first call to a valid certificate in Barking and Dagenham, East London: 2–3 working days to book, 2–4 hours per residential unit, longer for properties with older wiring or a large number of circuits, and the report issued the same day. Below is the full step-by-step timeline, plus how long you have to fix any faults.

EICRs issued in 2020–2021 expire by April 2026

Book early. If remedial work is needed you must allow up to 28 extra days for repairs and a re-test. Leaving it late risks a civil penalty of up to £40,000 per breach.

EICR timeline at a glance

To get booked in

2–3 days

Inspection on site

2–4 hours

Report issued

Same day

Step-by-step: getting an EICR in Barking and Dagenham

  1. 1

    Book the inspection

    Same day to book; 2–3 working days to attend

    Most registered electricians can attend within 2–3 working days of your call. Diaries fill up fastest in spring renewal season, so book ahead if your certificate is close to expiring.

  2. 2

    Arrange tenant access

    Built into your booking lead time

    The inspection needs access to every room, the consumer unit and often the loft. Give tenants at least 24 hours' written notice so the appointment is not wasted — a missed visit can add a week to the timeline.

  3. 3

    On-site inspection

    2–4 hours for a typical property

    The electrician tests every circuit, turning power off one circuit at a time. A studio takes around 2 hours; a larger house or HMO with more circuits can take a full day.

  4. 4

    Report issued

    Same day or within 24 hours

    The EICR is normally produced the same day or the next morning. A 'Satisfactory' result means you are compliant and no further work is needed.

  5. 5

    Remedial work (only if Unsatisfactory)

    Up to 28 days (sooner for C1 faults)

    Any C1 or C2 observation must be fixed and the property re-tested. C1 ('danger present') should be made safe immediately; all remedial work and re-testing must be completed within 28 days of the inspection.

  6. 6

    Serve the EICR on tenants

    Within 28 days of the inspection

    Give a copy of the report to existing tenants within 28 days, and to any new tenant before they move in. Keep dated proof of service — the council can request the report within 7 days of asking.

What can slow the timeline down?

EICR timeline in Barking and Dagenham — FAQs

How long does an EICR take in Barking and Dagenham?+

From booking to a certificate on file, allow about a week in Barking and Dagenham: 2–3 working days to get an electrician booked in, 2–4 hours per residential unit, longer for properties with older wiring or a large number of circuits, and the report issued the same day or within 24 hours. If the inspection is 'Unsatisfactory', remedial work and re-testing must be completed within 28 days.

How long does the EICR inspection itself take?+

The on-site inspection takes 2–4 hours per residential unit, longer for properties with older wiring or a large number of circuits. A studio or 1-bed flat is at the shorter end; larger houses and HMOs with more circuits take longer because every circuit is tested individually.

How quickly can I get an EICR booked in?+

Most registered electricians can attend within 2–3 working days. Renewal season in spring is busier, so if your current certificate is close to its five-year expiry, book as early as possible to leave room for any remedial work.

How long do I have to fix faults found in the EICR?+

If the report is 'Unsatisfactory', any C1 or C2 faults must be remedied within 28 days of the inspection — and C1 'danger present' faults should be made safe immediately. The electrician then re-tests and confirms the installation is satisfactory.

When do I have to give the EICR to my tenants?+

You must give a copy of the EICR to existing tenants within 28 days of the inspection, and to new tenants before they move in. If the local housing authority asks for it, you have 7 days to supply it.

Start the clock — get EICR quotes in Barking and Dagenham

Compare up to 3 verified, registered electricians in Barking and Dagenham. Free, no obligation.

Get Free EICR Quotes

Comparing prices first? See the EICR cost guide for Barking and Dagenham.